India Set to Commission First Two Hydropower Projects on Western Rivers After Suspending Indus Waters Treaty

13 November 2026 23:11 PM

NEWS DESK

File Photo

India is preparing to commission its first two hydropower projects on the western rivers of the Indus basin following the suspension of the Indus Waters Treaty with Pakistan.

The Indian government aims to operationalise the 1,000-megawatt (MW) Pakal Dul and 624-MW Kiru hydropower projects by the end of December.

Both projects are located in Jammu and Kashmir's Kishtwar district, with the Pakal Dul project being built on the Marusudar River, a tributary of the Chenab, and the Kiru project on the Chenab River.

India suspended the historic 1960 Indus Waters Treaty last April following the Pahalgam attack.

A senior official said that although commissioning, testing and the process of filling and draining the reservoirs would take some time, both projects were expected to reach full operational capacity within the next few months.

The official added that the suspension of the treaty meant that the design and operational restrictions previously imposed under the agreement were no longer applicable, helping accelerate the projects.

However, it remains unclear when, or whether, the treaty will be renegotiated.

Background of the Indus Waters Treaty

Under the 1960 treaty, India had exclusive rights over the eastern rivers of the Indus basin — the Ravi, Beas and Sutlej — which account for approximately 20 percent of the basin's total water.

Pakistan was granted rights over the three western rivers — the Indus, Jhelum and Chenab — which carry approximately 80 percent of the total water.

Kiru Hydropower Project

Built at an estimated cost of 42.87 billion Indian rupees, the Kiru project features a 135-metre-high dam and four generating units, each with a capacity of 156 MW.

Prime Minister Narendra Modi laid the foundation stone of the project in February 2019.

Pakal Dul Hydropower Project

The Pakal Dul project is being constructed on the Marusudar River, a tributary of the Chenab, at an estimated cost of 81.12 billion rupees.

The project includes a 167-metre-high dam and four generating units, each with a capacity of 250 MW.

Both run-of-the-river projects have been developed by Chenab Valley Power Projects, a joint venture between the National Hydroelectric Power Corporation (NHPC) and the Jammu and Kashmir State Power Development Corporation.

India's Future Hydropower Plans

India has an estimated hydropower potential of 18,569 MW across the western rivers but has so far developed only around 3,500 MW of capacity.

The country is planning several additional projects to expand its hydropower generation capacity.

Among them is the 540-MW Kwar project, which is expected to be completed by 2028. Work on the 850-MW Ratle project, meanwhile, has faced some delays.

Four other projects — Sawalkote, Kirthai-II, Dulhasti Stage-II and Uri-I Stage-II — have also been proposed.

India is additionally considering the construction of a 10-12-kilometre-long tunnel to divert water from the Chenab River towards the Ravi River.

The 206-MW Shahpurkandi project on the Ravi River is expected to become operational by mid-2027.